Water

Water Transmission Line

Completed in 2007 with a construction cost of $9,563,063, this project included the design and construction administration of approximately 23 miles of a 20- through 36-inch water transmission line to deliver water from the City of McKinney distribution system to the cities of Melissa, Anna, Van Alstyne and Howe, including meter stations for each city. Pictured are the layout of the line, a picture taken during construction, and a newspaper clipping from the Dallas Morning News highlighting the project.