All Projects
Central Fire Station Addition
A two-story, 5,000 s.f. addition to existing fire station.
- Client: City of Forney, TX
- Completion Date: December 2008
- Construction Cost: $920,784
Animal Shelter Expansion
2 new kennels, 40 indoor/outdoor pens each.
- Client: City of Sherman, TX
- Completion Date: May 2002
- Construction Cost: $315,000
Laboratory Building
6,000 s.f. laboratory building.
- Client: City of Sherman, TX
- Completion Date: February 2002
- Construction Cost: $600,000
Geotechnical Support for Main Street Extension
Geotechnical Support – slope stability.
- Client: City of Forney, TX
- Completion Date: July 2009
- Construction Cost: $1,500,000
Bachelor Kings Drainage Improvements
408 linear feet of concrete channel.
- Client: City of Terrell, TX
- Completion Date: August 2009
- Construction Cost: $185,773
Millard Paving and Drainage Improvements
4,000 square yards of 10″ thick reinforced concrete.
- Client: Town of Sunnyvale, TX
- Completion Date: April 2010
- Construction Cost: $335,231
Regal Drive Extension
37′ wide concrete street with integral curb.
- Client: City of Forney, TX
- Completion Date: May 2010
- Construction Cost: $458,091
RCISD Intermediate School Offsite Sewer Inspection
City of Fate/Royce City ISD Construction Observation.
- Client: City of Fate, TX
- Completion Date: February 2010
- Construction Cost: N/A
Structural Design of Barnes Bridge Pump Station
Structural calculations and modeling.
- Client: City of Mesquite, TX
- Completion Date: Under Design
- Construction Cost: $600,000